Question: You are the new project manager tasked with taking over for a project manager who left 6 weeks ago. Some of the numbers that you
You are the new project manager tasked with taking over for a project manager who left weeks ago. Some of the numbers that you find in your initial research are as follows:
Estimated project cost: $
Project timeline: weeks
This is week and accumulated costs are $ Additionally, only of the work has been completed.
What is the planned value?
Question options:
$
$
$
$
There is not enough information.
Step by Step Solution