Question: You are the operations manager for a building contractor employed by Sydney University which currently has six small projects awaiting assignment. Task times and due
You are the operations manager for a building contractor employed by Sydney University which currently has six small projects awaiting assignment. Task times and due dates are given in the table below. Assume that tasks arrive in the order shown and the start date is day 1.

i. Using appropriate performance metrics discussed in the course, compare the assignment sequence according to the First Come First Served (FCFS) and Shortest Processing Time (SPT) priority rules. Which assignment rule would you recommend to your boss? Why? Show all working. (12 marks)
ii. Should your boss accept your recommendation, what caveats should you make him aware of? Discuss issues specific to the assignment methods used here as well as with rule-based sequencing systems more generally. (3 marks)
Task Project Processing Time (Days) Project Due Date (Days) T1 6 22 T2 12 14 T3 14 30 T4 2 18 T5 10 25 T6 4 34Step by Step Solution