Question: You are the project manager for a construction project. Your foreman informs you that, due to the humidity, the concrete will need to cure for
You are the project manager for a construction project. Your foreman informs you that, due to the humidity, the concrete will need to cure for an additional hours before the framing can begin. To accommodate the requirement, you add time to the framing activity.
delay
lead
slack
lag