Question: You are the Project Manager for a consumer research database project. You have just finished putting together all the various plans into an integrated complete
You are the Project Manager for a consumer research database project. You have just finished putting together all the various plans into an integrated complete document that the team will use to guide them in creating the project work. What step have you just completed?
A) Project Management Plan execution
B) Developing the Project Management Plan
C) Charter signoff
D) Schedule development