Question: You are the project manager for a project with a budget of $250,000 and a target date of six months. Halfway through the project, you
You are the project manager for a project with a budget of $250,000 and a target date of six months. Halfway through the project, you find that you spent $175,000. What is the status of your project? Calculate SPI and CPI.
Management promised a completion date for the project to a customer, and you know that the completion date is impossible to meet. What do you do?
One of the project risks"bad/incomplete data from distributors"has occurred. What do you do?