Question: You are the Project Manager for a small project. You need to build a structure in 7 days. Today is the end of day 4
You are the Project Manager for a small project. You need to build a
structure in days. Today is the end of day The following is an extract
from the Site Manager's Report.
a Fill the table provided belowshow your calculations
b Based on the data, please explain if we are expected to be
underbudget or overbudget at the end of the project.