Question: You are the project manager for a software development project. You are reviewing the stakeholder register, and it shows that there are 15 total stakeholders
You are the project manager for a software development project. You are reviewing the stakeholder register, and it shows that there are 15 total stakeholders on the project. How many channels of communication are there?
A.15
B.112
C.105
D.210
E.92