Question: You are the project manager for a software development project that has a budget of $1M. Your client has asked you for a status update

You are the project manager for a software development project that has a budget of $1M. Your client has asked you for a status update on the project. Through your recent monitoring and control activities, you have established that your Planned Value was $300,000 and the Schedule Variance is +$10,000. You have spent $350,000 on the project so far.
Is the project moving ahead on time? Explain how you determined this.
Is the project spending within budget? Determine using CV or CPI.
By the time the project will complete, what will be the difference between budget and actual cost, i.e. VAC?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To know if the project is moving ahead on time or not we have to use the calculate Schedule Variance ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock