Question: You are the project manager for a software product and you project is in the execution phase. You have learned that one of your developers
You are the project manager for a software product and you project is in the execution phase. You have learned that one of your developers has started adding some new features to the deliverable that they are working on. What is the best action you should take?
| a. | Tell the developer to delete the code corresponding to theses features because this is a scope creep and scope creep is not permitted | |
| b. | Review the added features with the developer, e.g., what are these features and how much time will they take, then make the necessary updates to the WBS, the WBS dictionary, and the schedule. Tell the developer that in the future they should get approval from you before adding new features. | |
| c. | Determine where the request for new features came from and process the change request through the integrated change request process | |
| d. | Contact the developers functional manager and ask their manager to replace the developer with another developer |