Question: You are the project manager for a software project to make a new software for a company. During the risk management process, you used the
You are the project manager for a software project to make a new software for a company. During the risk management process, you used the probability-impact matrix to prioritize the risks. During which stage of the risk plan, you would do this prioritization? (explain your answer)
a. Risk Management Plan
b. Risk Response Plan
c. Risk Breakdown Structure
d. Risk Monitoring
e. Risk Analysis
f. Risk Indentification Plan