Question: You are the project manager for a software project. You created a Risk Management Plan , identified number of risks with project team and stakeholders.
You are the project manager for a software project. You created a Risk Management Plan , identified number of risks with project team and stakeholders. The following figure shows the probability and impact matrix you created. What is the most important risk that the project manager needs to take into consideration ?

a. Risk A
b. Risk D
c. Risk C
d. Risk B
Risk B D E Probability Impact 0.75 3,500 0.33 -27,000 0.5 -20,500 0.4 23,000 0.15 -22000 P* 2625 -8910 -10250 9200 3300