Question: You are the project manager for a team of 7 developers, and you have decided to use XP because of the small size of the

You are the project manager for a team of 7 developers, and you have decided to use XP because of the small size of the team and the type of the project. At the end of iteration 1, the following information has been collected for the total work done by each developer (Note: not every developer is full-time, as observed from the information below)

Original estimate 4 days 8 days 5 days 4 days 9 days 10 days 7 days Actual time needed 5 days 10 days 10 days 8 days 9 days 6 

If 2-calendar-week iterations are used here, what is the project velocity? Assume there were no official holidays in iteration 1

You want to schedule iteration 2 from the work repository below. Using the project velocity from iteration 1, and assuming 1 long weekend (3-day weekend) in the next 2 weeks, which tasks will make it to iteration 2? Ignore actual assignment of the tasks to specific develop

Original estimate 4 days 8 ays 5 days 4 days 9 days 10 days 7 days Actual time needed 5 days 10 days 10 days 8 days 9 days 6 days 8 days

Step by Step Solution

3.45 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

If 2calendarweek iterations are used here what is the project velocity Assume there were no official ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!