Question: You are the project manager for an IT project. You have just received cost control information that shows the project's cost variance (CV) is R

You are the project manager for an IT project. You have just received cost control information that shows the project's cost variance (CV) is R 30 000 and the project's schedule variance (SV) is - R5 000. What can you deduce about the project expenses and schedule