Question: You are the project manager for the ClockWatch project. You have decided to construct a tornado diagram to review the sensitivity of resource costs with

You are the project manager for the ClockWatch project. You have decided to construct a tornado diagram to review the sensitivity of resource costs with the project sponsor. The base formula for this project is as follows:

Resource Cost = Operations Cost + Legal Cost + HR Cost + Marketing Cost

The data is as follows (shown in thousands of dollars):

O M P
Operations 4.5 8.5 12
Legal 3.5 4 7
HR 0.5 3 6
Marketing 0.25 0.5 1

What is the result of this fair ranking of the value and decision sensitivity of the decision problem in the example? Which organization is most sensitive to the sponsor's decision and which is the least sensitive?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!