Question:
You are the project manager of a new project, and you know from past experience that one of the key stakeholders on the project constantly requests changes throughout a project. You want to avoid this situation. What should you do
A. Observe this stakeholder's involvement, and if this becomes an issue, then escalate to the sponsor.
B. Avoid communicating too many results with this stakeholder.
C. The less they know, the fewer changes they will request.
D. Involve the stakeholder as early as possible and request their input regularly throughout the project.
E. Consider this situation as a risk to the project and update the risk register.