Question: You are the project manager of a project developing a new product for your company. The project has seven tasks, each with a finish -

You are the project manager of a project developing a new product for your company. The project has seven tasks, each with a finish-to-start relationship. Below is project baseline information indicating the planned schedule and budgeted cost of each task. The Product Release 1.0 row is the summary task that summarizes the tasks below it.
Planned
Task Name % Complete Baseline Duration Baseline Start Baseline Finish Baseline Cost
Product Release 1.00%240 days 01/08/2412/07/24 $295,000.00
Requirements 0%30 days 01/08/2402/16/24 $30,000.00
Design 0%60 days 02/19/2405/11/24 $70,000.00
Proof of Concept 0%30 days 05/14/2406/22/24 $45,000.00
Build Product 0%45 days 06/25/2408/24/24 $60,000.00
Test Product 0%45 days 08/27/2410/26/24 $60,000.00
Deploy Product 0%30 days 10/29/2412/07/24 $30,000.00
Product Release Complete 0%0 days 12/07/2412/07/24 $0.00
The project is currently in the middle of the execution phase and the date is June 22th. The information in the chart below provides the schedule and cost information to-date and the Gantt chart reflects the project's current progress and estimated completion dates.
Actual
Task Name % Complete Actual Duration Actual Start Actual Finish Actual Cost
Product Release 1.050%122 days 01/08/24 NA $147,000.00
Requirements 100%35 days 01/08/2402/23/24 $32,000.00
Design 100%60 days 02/26/2405/17/24 $70,000.00
Proof of Concept 90%27 days 05/20/24 NA $45,000.00
Build Product 0%0 days NA NA $0.00
Test Product 0%0 days NA NA $0.00
Deploy Product 0%0 days NA NA $0.00
Product Release Complete 0%0 days NA NA $0.00
image.png
Excel Workbook Requirements
Include the first and last name(s) of the student(s) that prepared the workbook in the file name (ex. Earned Value Kathy Majeske.xlsx)
Use appropriate formulas to calculate the following Earned Value measures:
SV
SPI
CV
CPI
EAC
ETC
BAC
VAC

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!