Question: You are the project manager of a project developing a new product for your company. The project has seven tasks, each with a finish -
You are the project manager of a project developing a new product for your company. The project has seven tasks, each with a finishtostart relationship. Below is project baseline information indicating the planned schedule and budgeted cost of each task. The Product Release row is the summary task that summarizes the tasks below it
Planned
Task Name Complete Baseline Duration Baseline Start Baseline Finish Baseline Cost
Product Release days $
Requirements days $
Design days $
Proof of Concept days $
Build Product days $
Test Product days $
Deploy Product days $
Product Release Complete days $
The project is currently in the middle of the execution phase and the date is June th The information in the chart below provides the schedule and cost information todate and the Gantt chart reflects the project's current progress and estimated completion dates.
Actual
Task Name Complete Actual Duration Actual Start Actual Finish Actual Cost
Product Release days NA $
Requirements days $
Design days $
Proof of Concept days NA $
Build Product days NA NA $
Test Product days NA NA $
Deploy Product days NA NA $
Product Release Complete days NA NA $
image.png
Excel Workbook Requirements
Include the first and last names of the students that prepared the workbook in the file name ex Earned Value Kathy Majeske.xlsx
Use appropriate formulas to calculate the following Earned Value measures:
SV
SPI
CV
CPI
EAC
ETC
BAC
VAC
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock