Question: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before

You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week.

ACTIVITY

Immediate Predecessor (s)

NORMAL TIME (NT)

CRASH TIME (CT)

Normal Cost (NC)

Crash Cost (CC)

A

--

2

1

7,000

10,000

B

--

2

2

3,000

3,000

C

A

3

1

12,000

40,000

D

B

3

2

12,000

28,000

E

C

1

1

8,000

8,000

F

D, E

5

3

5,000

15,000

G

E

3

2

9,000

18,000

A - Before crashing, the project duration is _________ week(s).

B- The total cost of the project if we do nothing is $ __________ (round to the nearest dollar).

C- The minimum cost schedule is ________ week(s) (enter response as integer) .

D - The minimum cost schedule resulted in saving $________________ (enter response as integer).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!