You are the risk manager for a tech company, and you are evaluating two possible projects: Project
Fantastic news! We've Found the answer you've been seeking!
Question:
You are the risk manager for a tech company, and you are evaluating two possible projects: Project X and Project Y. The following table shows the possible outcomes and their probabilities for each project:
Outcome | Project X (probability) | Project Y (probability) |
---|---|---|
$50,000 profit | 0.4 | 0.1 |
$20,000 profit | 0.3 | 0.5 |
No profit | 0.3 | 0.4 |
Assuming a risk-free rate of 3%, calculate the expected value, variance, standard deviation, and Sharpe ratio of each project. Based on these metrics, which project would you recommend?
Related Book For
Fundamentals of Financial Management
ISBN: 978-0324597707
12th edition
Authors: Eugene F. Brigham, Joel F. Houston
Posted Date: