Question: You are three months into a six - month project. Assume that the budget burn rate is constant. The budget at completion ( BAC )

You are three months into a six-month project. Assume that the budget burn rate is constant. The budget at completion (BAC) is $120,000. AV = $65,000. The SPI =1.2. What is the CPI of this project?