Question: Given the following project activity table, what is the late start of activity L ? Activity Duration Dependency H 3 I 2 H J 2

Given the following project activity table, what is the late start of activity L?
Activity Duration Dependency
H 3
I 2 H
J 2 H
K 4 I
L 6 J
M 4 K,L