Question: You are using a triangular PERT formula to estimate an activity's duration. What information do you need to complete this estimate? a the activity's early
You are using a triangular PERT formula to estimate an activity's duration. What information do you need to complete this estimate? a the activity's early start date and early finish date b the optimistic, most likely, and pessimistic values for the activity c the activity's late start date and late finish date d the activity's predecessor and successor activities e Leave blank for now. I'll submit my answer later