Question: Using the Critical Path Method ( CPM ) and PERT: a ) Create the activity network diagram and calculate the mean time for each activity.

Using the Critical Path Method (CPM) and PERT:
a) Create the activity network diagram and calculate the mean time for each activity.
b) Use these mean times as the duration for each activity and present the updated network diagram.
c) Determine the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity and identify the critical path.
d) Calculate the float time for each activity.
e) Compute the variance for each activity and find the sum of variances for all activities with zero float time (using pert formula)
Note: (Accuracy of values: to four decimal places)
Activity Immediate predecessor Optimistic Time Most Probable Time Pessimistic time Mean Time (PERT Formula) Float Time Variance (Pert Formula)
A -6710
B -8912
C A 8810
D B 578
E B 367
F C,D 121314
G E,D 81218
H F,G 101721
I G,H,E 111214

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!