Question: You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value. That means the project

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value. That means the project is _____.
Select an answer:
over budget
ahead of schedule
under budget
behind schedule