Question: You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.

A) Your CEV is RM380,000, while your CAC is RM460,000, calculate your CPI and explain what does it indicate.

B) Based on the above data, what is your CV?

C) Calculate your FCAC using both methods. Your total budget is RM 570,000. Explain the difference?

D) Calculate TCPI, and explain what it means.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!