Question: You are working for a contractor that has a contract for construction of a new hospital. One of the project tasks is the compacted fill

You are working for a contractor that has a contract for construction of a new hospital. One
of the project tasks is the compacted fill for the parking lot. Initial investigation of the
project plan indicates that 30,000 compacted cubic yards are required for the fill. You
have selected a source for the fill material and the soil test report indicates the bank density
to be 2750 pounds per cubic yard and the loose density to be 2200 pounds per cubic yard,
and the compacted density to be 3500 pound per cubic yard.
a. What is the percent shrinkage for the fill material?
b. What is the percent swell for the fill material?
c. How many BCY do you have to excavate?
d. How many LCY do you have to haul?
e. If the unit cost of excavation and fill process is $12.5 per CCY, how much is the
total cost of this component of the project?
You are working for a contractor that has a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!