Question: You are working on a project on your creative director hosts or some new images to be used on the website you hadn't budgeted for

You are working on a project on your creative director hosts or some new images to be used on the website you hadn't budgeted for these costs and the time he taking to come up with these images is coming in significantly higher than expected thankfully you have some money put aside but you will need to get the sponsor to approve access to those fans what is the source of funds that you will be making use of to take care of this cost
A. fee reserved
B. task cost
C. project reserve
D. cost baseline
E. managerial reserve
 You are working on a project on your creative director hosts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!