Question: You are working on a project to be completed in 2 4 months and the total cost of the project is $ 2 2 0

You are working on a project to be completed in 24 months and the total cost of the project is $220,000. Twelve months have passed and 100,000$ has been spent, and 60% of the work has been completed so far. What is the TCPI?