Question: You are working on a project to implement a new set of business processes for your company. Senior management wants the project to proceed, but

You are working on a project to implement a new set of business processes for your company. Senior management wants the project to proceed, but they have determined that critical staff members do not have the time to meet with you and your team and discuss the validity of the new processes you have drafted and won't prior to the implementation date your sponsor has set for the project. As a result, you have concluded there is an overall project risk. Is that risk (a) the ability to deliver or (b) the ability to control the project?