Question: you are working on an undefinitized contract action (UCA) for the purchase of cargo hooks for the CH-47 Chinook helicopter. The not-to-exceed (NTE) price is
you are working on an undefinitized contract action (UCA) for the purchase of cargo hooks for the CH-47 Chinook helicopter. The not-to-exceed (NTE) price is $7,000,000. Can you obligate the total amount at time of award? Why or why not?
Step by Step Solution
3.39 Rating (146 Votes )
There are 3 Steps involved in it
In an undefinitized contract action UCA the total amount cannot be obli... View full answer
Get step-by-step solutions from verified subject matter experts