Question: (You can do answer only) Arlington company makes engine brackets, which including only two processes: Forming and Drilling Its Availability is Availability: 8 hours per

(You can do answer only)

Arlington company makes engine brackets, which including only two processes: Forming and Drilling

Its Availability is "Availability: 8 hours per shift with a 30-minute lunch break "

Its Average Daily Demand from customers is 3000 units per day.

The value stream table is as follows:

Step 1: Forming

Cycle time =

11

seconds

Setup Time =

3

Minutes

Uptime =

100%

Operators =

1

WIP (before Forming) =

4000

units

Step 2: Drilling

Cycle time =

10

seconds

Setup Time =

2

Minutes

Uptime =

100%

Operators =

1

WIP (before Drilling) =

5000

units

What is the total production lead time of the value stream?

Group of answer choices

3 days

7 days

17 days

5 days

7 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!