Question: Seattle manufactures engine brackets, which including only two processes: Forming and Drilling Its Availability is Availability: 8 hours per shift with a 30-minute lunch break

Seattle manufactures engine brackets, which including only two processes: Forming and Drilling

Its Availability is "Availability: 8 hours per shift with a 30-minute lunch break "

Its Average Daily Demand from customers is 3000 units per day.

The value stream table is as follows:

Step 1: Forming

Cycling time =

11

seconds

Setup Time =

3

Minutes

Uptime =

100%

Operators =

1

WIP (before Forming) =

4000

units

Step 2: Drilling

Cycling time =

10

seconds

Setup Time =

2

Minutes

Uptime =

100%

Operators =

1

WIP (before Drilling) =

5000

units

What is the total processing time of the value stream?

Group of answer choices

32 seconds

21 seconds

35 seconds

42 seconds

36 seconds

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!