Question: You can see the project network below. After detailed analysis of the project, you found the expected activity times ( in days ) for all

You can see the project network below. After detailed analysis of the project, you found
the expected activity times (in days) for all ten activities. These numbers are
incorporated into the project network.
Use the given information to answer to the following questions.
(a) Fill in the activity nodes.
(b) The critical path is E-H.H.J],. If you get more than one critical path,
please select the upper one. For example, if you have A-C-G-J and B-H-I-J, then you
have to select A-C-G-J.
(c) The expected optimal completion time is E(t)=
days.
(d) Based on the results for the questions (a)-(b), answer the following questions:
How many days the activity A can be delayed without increasing the expected
project completion time?
Is it possible that the activity J is delayed without increasing the expected project
completion time? Select an answor vv
(e) The following table shows the calculated expected variance for each activity.
 You can see the project network below. After detailed analysis of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!