Question: You can see the project network below. After detailed analysis of the project, you found the expected activity times ( in days ) for all
You can see the project network below. After detailed analysis of the project, you found
the expected activity times in days for all ten activities. These numbers are
incorporated into the project network.
Use the given information to answer to the following questions.
a Fill in the activity nodes.
b The critical path is HHJ If you get more than one critical path,
please select the upper one. For example, if you have ACGJ and BHIJ then you
have to select
c The expected optimal completion time is
days.
d Based on the results for the questions ab answer the following questions:
How many days the activity A can be delayed without increasing the expected
project completion time?
Is it possible that the activity is delayed without increasing the expected project
completion time? Select an answor
e The following table shows the calculated expected variance for each activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
