Question: You can use the book's method or the method provided in Module 3 Homework. Let me know which method you used here. HomeDepots Global Supply

You can use the book's method or the method provided in Module 3 Homework. Let me know which method you used here.

HomeDepots Global Supply produces Product A and needs to ship 1000 units of Product A at the beginning of week 4, 800 at the beginning of week 5, 1200 at the beginning of week 6, and 500 at the beginning of week 8.

Product A is manufactured using the following components; 4 units of component D, 2 units of component J, and 12 units of component Ks (This is the BOM for one A)

On hand balances: D 100 units, J 20,000 units , and K 50,000 units. Lead times, regardless of quantity, for all components are shown below.

Components

Lead times

D

2 weeks

J

4 weeks

K

1 week

Prepare the master schedule and a materials requirement plan using lot-for-lot ordering for all items.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!