Question: You created a table and updated the project as shown in Table 1 below. 1. Calculate the following: a. Cost variance (CV) b. Schedule variance
You created a table and updated the project as shown in Table 1 below. 1. Calculate the following: a. Cost variance (CV) b. Schedule variance (SV) c. Total variance (TV) d. Percent cost variance (PCV) e. Percent schedule variance (PSV) f. Percent total variance (PTV) g. Cost performance index (CPI) h. Schedule performance index 2. Explain the status of the project based on the data collected and calculated in question 1. Tahle 1- Data for residential huildino
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
