Question: You decided that you can start a task 5 days before the completion of a predecessor task. The is an example of 1. Merge activity

You decided that you can start a task 5 days before the completion of a predecessor task. The is an example of

1. Merge activity

2.Burst activity

3. Lead

4. Lag

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer