Question: You decided that you can start a task 5 days before the completion of a predecessor task. The is an example of 1. Merge activity
You decided that you can start a task 5 days before the completion of a predecessor task. The is an example of
1. Merge activity
2.Burst activity
3. Lead
4. Lag