Question: You have a project worth $ 4 0 0 , 0 0 0 . Four months have passed and $ 2 0 0 , 0
You have a project worth $ Four months have passed and $ has been spent. Upon closer review, you find that only of the work is completed; however, as per the schedule, of the work should have been completed. Determine the Schedule Performance Index SPI and CPI. Comment on the project performance.