Question: You have an activity in your value stream map with the characteristics shown below. The plant works 6.5 hours per day 5 days per week.

You have an activity in your value stream map with the characteristics shown below. The plant works 6.5 hours per day 5 days per week. The weekly demand for the product is 39,000 units. With a process time (PT) of 5 seconds, calculate the utilization (CT/TT).

You have an activity in your value stream map

FTE 2 s/U. 10 Min B/S - 40 . Util