Question: A process takes 81 seconds. There are 10 workers in the section who each spend 0.69 of their time working on this process. In each
2.The plant works 8 hours per day 5 days per week. The weekly demand for the product is 87,855 units. What is the Takt Time in seconds?
3.The plant works 9 hours per day 5 days per week. The weekly demand for the product is 13,344 units. With a cycle time (CT) of 6 seconds, calculate the utilization (Cycle Time/Takt Time). Enter your answer as a decimal (e.g., if utilization is 50% enter it as .50).
4.The only customer service employee per shift is allowed to spend 0.7 of the 8-hour workday (FTE = 0.7) on a task with a process time of 35 Seconds. What is the cycle time for this task?
Step by Step Solution
3.55 Rating (166 Votes )
There are 3 Steps involved in it
1 To calculate the cycle time per unit at 100 capacity we need to follow these steps 1 Calculate the Total Time Spent on the Process by All Workers Since each worker spends 069 of their time on this p... View full answer