Question: You have been appointed program manager for the closing phase of the systems integration program for Globus Enterprises, under contact to the government of Moldova.
You have been appointed program manager for the closing phase of the systems integration program for Globus Enterprises, under contact to the government of Moldova. As the closing program manager, you must ensure that all administrative activities are complete. One best practice is to review the
1 point
a. Program work breakdown structure (PWBS)
b. Business case
c. Program management plan
d. Benefits management plan