Question: ) You have been assigned a task by the Armed Forces to Procure a Newultra-modernWar Tankbut the Armed Forces are not satisfied with the Navigation
)You have been assigned a task by the Armed Forces to Procure a Newultra-modernWar Tankbut the Armed Forces are not satisfied with the Navigation System of the tank as it is one of the key components and want to change it as per their requirements.Under which Procurement category would you place such a Project? Provide Rationale for your choice.