Question: You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels they have

You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels they have a basic grasp on their requirements but also feels that they will know more as the project progresses. Using your knowledge of life cycle models, identify two models that may work based on your knowledge of the project.

The scope of the project is as follows:

  1. Requirement 1: 3 bedrooms
  2. Requirement 2: 2.5 bathrooms
  3. Requirement 3: Pool
  4. Requirement 4: 2 patios, one patio should be enclosed

  1. Build a network diagram
  2. Identify the early start, early finish, late start late finish for each activity
  3. Identify the critical path
  4. Identify the duration of the critical path
  5. What is the float of Activity B
  6. What is the float of Activity H
  7. Activity Predecessor Duration in Days
    A Start 3
    B Start 6
    c A, B 12
    D B 5
    E D 4
    F C 6
    G E,F 8
    H E 7
    I H 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!