Question: You have been developing a next generation electric engine for high - speed electric trains. The client is worried and asks you to provide him

You have been developing a next generation electric engine for high-speed electric trains. The client is worried and asks you to provide him with the progress and forecasting report as soon as possible. So you start collecting information such as % complete, the start and finish dates of scheduled activities, number of change requests, number of defects, actual costs, actual durations, etc. These are examples of:
Scope baseline
Work metrics management
Work performance data
Work process analysis