Question: You have been developing a next generation electric engine for high - speed electric trains. The client is worried and asks you to provide him
You have been developing a next generation electric engine for highspeed electric trains. The client is worried and asks you to provide him with the progress and forecasting report as soon as possible. So you start collecting information such as complete, the start and finish dates of scheduled activities, number of change requests, number of defects, actual costs, actual durations, etc. These are examples of:
Scope baseline
Work metrics management
Work performance data
Work process analysis