Question: You have been hired to do maintenance work on 4 servers. Each server is scheduled to take one day to complete at a cost
You have been hired to do maintenance work on 4 servers. Each server is scheduled to take one day to complete at a cost of $600 per server. At the end of day 2, you have spent $1100 and 1.5 servers are complete Fill in the following table with the appropriate earned value amounts, assuming that current sending will continue. Earned Value Planned Value Earned Value Actual Cost Cost Variance Schedule Variance Cost performance Index Schedule performance Index Estimate at Completion (EAC) Estimate to completion (ETC) Variance at completion Amounts
Step by Step Solution
3.44 Rating (157 Votes )
There are 3 Steps involved in it
Earned Value Table Earned Value Amounts Planned Value 4 servers 600server 2400 Earned Value 15 servers 600server 900 Actual Cost 1100 Cost Variance Ac... View full answer