Question: You have decided to enter into a time and materials contract with a supplier for your project. The project will require two different types of

You have decided to enter into a time and materials contract with a supplier for your project. The project will require two different types of labor categories, the first which charges $200 per hour and the second which charges $175 per hour. The project requires 50 hours of the first labor category and 40 of the second. You will also purchase $5,000 of tools and equipment with no fee and $25,000 of materials with a 2% fee added on. What will you owe on this contract?