Question: You have identified important risks and planned the appropriate responses. Some risks ( e . g . possibility of natural disasters impacting the project )
You have identified important risks and planned the appropriate responses. Some riskseg possibility of natural disasters impacting the project have been documented and accepted in your risk management plan. What are the remaining risks called?
Question Answer
a
Secondary Risks
b
Unidentifiable Risks
c
Residual Risks
d
Inherent Risks