Question: You have just begun executing work on a project when your customer asks you what the impact of an additional scope requirement will be .

You have just begun executing work on a project when your customer asks you what the impact of an additional scope requirement will be. When considering the triple constraints, what are two areas that will likely be impacted by an increase in scope?
Cost & Schedule
Cost & Risk
There wont be any impact if you just started executing the work.
Schedule & Risk