Question: You have just installed a new process for making aspirin that is much more efficient than your old one. You set the performance standard at

You have just installed a new process for making aspirin that is much more efficient than your old one. You set the performance standard at 1,000 cases per day, double your old rate. Production on the first day tops 5,000 cases, exceeding all expectations. What should you do next?
a. Revise the performance standard.
b. Lay off 80 percent of your workers.
c. Take corrective action.
d. Reduce the speed of the equipment.