Question: You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?
Multiple Choice
There are multiple critical paths.
The analysis is performed incorrectly.
More than one path is optimal.
Only one path is optimal.