Question: You have signed a contract to build a garage for the Lloyds. You will receive a $ 2 0 0 bonus per day you saved

You have signed a contract to build a garage for the Lloyds.
You will receive a $200 bonus per day you saved if the project takes less than 29 days.
The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 29 days.
What is the expected project duration?
ID Predecessor Duration
A _5
B A 3
C B 8
D B 7
E C 5
F C 8
G D 7
H E, F, G 2
I H 5
Answer:
Question 43
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the critical path?
a.
D-E-F-G-H-I
b.
A-B-C-F-H-I
c.
A-B-C-E-H-I
d.
A-B-D-G-H-I
e.
A-B-C-D-E-F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!