Question: You have signed a contract to bulld a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working

You have signed a contract to bulld a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clouse in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities. IDABCDEFGHIJKDescriptionPreparesitePourfoundationErectframeRoofWindowsDoorsElectricalRough-inframeDooropenerPaintCleanupPredecessorNoneABCCCCD,F,GF,GH,IJTime(days)61523516326 \begin{tabular}{ll|l} \hline The project will take & & \\ \hline The critical activities are & & days. \\ \hline The late start on Activity E is & days. \\ \hline The slack on Activity E is & days. \\ \hline The slack on Activity F is & days. \\ \hline Thetivity D is & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts